Southampton Central Station

Image representing Southampton Central Station from ASH Construction Group Ltd

ASH Construction Group supported R J Power at Southampton Central Station during Weekend 32. The primary task was to install 8 CMS sleepers around the S&C at Southampton Central Station. This installation was critical to our client & had to be completed by 08:00 on the Sunday morning to allow the team from R J Power to install their new DC power cables. 

ASH-CG ensured that the installation was carried out meticulously including Kango packing & ballast profiling removal of old sleepers from site. The site was handed to the   R J Power HV team on time at 08:00. 