Hope Valley Project

Image representing Hope Valley Project from ASH Construction Group Ltd

During a recent 9-day blockade for the Hope Valley Project, ASH-CG was honoured to assist one of our respected clients by delivering three distinct work packages. 

The first package was the Stressing S&C & Plain line on Bamford Loop - Our works included the installation of closure rails to eliminate air gaps and the completion of plain line welding across 9 welds, along with the stressing of the new S&C and plain line circa 1/2m of stressing. 

The second work package entailed the installation of a new turnout and traps at Grindleford, together with the associated plain line, which included all design tamping. 

The final package involved IBJ recoveries, specifically the recovery of 9 pairs of IBJs and the associated welding with L1 stressing. 

All tasks were accomplished safely, without any incidents or accidents. 