Client: DLR / Principal Contractor Oversight
Duration: 22 July – 10 August 2025
Scope
- Delivery and installation of new 60ft rails and 9.144 Breather Blades & Track Components
- Replacement of a Structural Breather Switch Blades in Engineering Hours
- Welding programme (W1–W24), grinding, and ultrasonic testing & Visual Inspections
- Installation of clips, fishplates, Robels, clamps, and Netlon fencing
- Completion of clamp inspections, conductor survey, and PTD–LCA amber trolley run
- Site clearance, tool recovery, and safe handback
- Removal of redundant rail and scrap management